Near West Design Review Case Report

PAUL LAURENCE DUNBAR SCHOOL

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Near West Case #  NW 2010-030

Address: 2200 West 28th Street
Owner/Rep: Hollie Dellasanti, Cleveland Metropolitan School District
Architect: Anne Hartman, Ralph Tyler Companies, Inc.
Description: Construct 2-story, 64,300 S.F. school building accommodating 450 pre-K thru 8th grade students
Notes:  
Preliminary steps involve demolition of existing Dunbar School building (already underway), abatement of site (completed), and grading and seeding of site in preparation for new building construction, which is scheduled to begin in January 2012. Sponsor has salvaged 2,500 bricks to be used in nearby neighborhood community gardens.

Proposed new building materials will primarily be masonry - combination of color and textured brick/block as well as accents of colored metal panels. The site will include separate drop-off areas for students arriving by car vs those arriving by bus. Other site features include a playground and open grass areas and locations for community gardening. The project will have LEED Silver designation.

Committee Actions/Submissions

Committee: BRD CPC
Action Date: July 27, 2011
Action Type: Approved
Conditions/Notes:  
Near West Design Review Committee approved changes to previously approved site plan, building elevations and exterior details, as submitted.
Committee: BRD CPC
Action Date: July 21, 2011
Action Type: Revised Plan Submission
Conditions/Notes:  
Committee: BRD CPC
Action Date: April 1, 2011
Action Type: City Planning Commission Approval
Conditions/Notes:  
Committee: BRD CPC
Action Date: March 9, 2011
Action Type: Revised Plan Submission
Conditions/Notes:  
Committee moved to approve the final design development drawings for the school, including site layout, building massing and materials, w/understanding that the sponsor will:

1. Explore moving the angled, head-in parking spaces in front of the Pre-K entrance slightly to the west along Monroe Avenue to eliminate sight line issues due to the presence of an existing mature street tree. It was further suggested that the installation of a mirror be explored to assist motorists in backing out of the angled spaces.

2. Use metal halide-style lighting fixtures for site lighting.

3. Re-examine the 4' space between floors, which the Committee felt was too generous and resulted in the building appearing taller than perhaps it need be. One possible way to accomplish this objective would be to increase the height of the windows along the first floor.
Committee: BRD CPC
Action Date: November 5, 2010
Action Type: City Planning Commission Approval with Conditions
Conditions/Notes:  
Incorporate a study of sidewalk conditions on perimeter blocks (all four sides)
Committee: BRD CPC
Action Date: October 27, 2010
Action Type: Conceptual Approval
Conditions/Notes:  
Committee approved project's schematic design, including site layout, building massing, and materials w/understanding that sponsor will re-study: (1) wall transparency issues along footpath adjacent to gymnasium; and (2) proposed color palette for masonry "B" materials. Sponsor agreed to furnish a perspective drawing that will provide a clearer depiction of the building's northwest and west facades.
Committee: BRD CPC
Action Date: October 20, 2010
Action Type: Plan Submission
Conditions/Notes: