Project Information

Euclid Corridor Case #  EC 2010-037

Address: Euclid Avenue between stokes and Martin luther king
Owner/Rep: Chris Bongorno
Architect: MSI Design
Description: New Building institutional
Notes:  

Committee Actions/Submissions

Committee: BRD CPC
Action Date: April 23, 2010
Action Type: Plan Submission
Conditions/Notes:  
applicant was seeking concept approval. The commission concurred with committees response and allowed for concept approval with the understanding that addition study must done regarding aesthetic elements of the project to properly convey the message that the projects seeks to convey. concept approval given by commission
Committee: BRD CPC
Action Date: April 22, 2010
Action Type: Conceptual Approval
Conditions/Notes:  
committee had multiple concerns regarding public's ability to identify meaning of proposal. Understanding the overall concept from an aerial view and the historic significance of the proposal. committee determined that the actual aesthetic elements of the proposal be studied further and determined that they would allow concept approval with the understanding that aesthetic elements of the project must be further developed.
Committee: BRD CPC
Action Date: April 12, 2010
Action Type: Plan Submission
Conditions/Notes:  
Plans submitted to UCI