DRC Home | Committees | Applicants Guide (PDF) | Submittals Checklist (PDF) |Application Form (PDF) | Agendas

Euclid Corridor Design Review Case Report

TRIANGLE BUILDING POD 1 RENNOVATIONS

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Euclid Corridor Case #  EC 2009-006

Address: 11457 mayfield road
Owner/Rep: Paul Volpe
Architect: City Archtecture
Description:
Notes:  
project represents phase one of a more extensive building renovation. project was signed of on administrativley due to the scale of the proposed improvements with only one unit being renovated. The one unit will serve as a template for all of the subsequent units. Committee will review the overall strategy on April 2nd permit applications will be needed for the full scale renovations that will occur as phase three of the overall development.

Committee Actions/Submissions

Committee: BRD CPC
Action Date: March 12, 2009
Action Type: Plan Submission
Conditions/Notes:  
Committee: BRD CPC
Action Date: March 12, 2009
Action Type: Administrative Approval
Conditions/Notes: